Metal Roof Waterproofing — Vauxhall, London SW8
From failing roof to finished system



The Challenge
Profiled sheet roofs rarely fail across the sheet. They fail at the joints, and this roof had every joint a roof can have, packed into a small area. Six barrel-vault rooflights sit in raised kerbs across the pitch, each one a perimeter where two materials meet and move at different rates. A section of black felt abutted the sheeting at the low end. Side laps, end laps and fastener heads ran the length of every bay.
Between the buildings the roof sits in near-permanent shade, so it never fully dries. Organic growth had colonised the troughs and was holding moisture against the surface instead of letting it run off — the condition that ages a coated or uncoated sheet faster than anything else.
Replacing the roof would have meant scaffolding a courtyard with no access, closing a trading gym and re-sheeting over occupied space. For sheets that were structurally sound, that was the wrong-sized answer.

Project file

Book a free survey and we’ll come back with a fixed price for your own roof.
The Solution — step by step
Why overcoat rather than re-sheet?
On an ageing profiled sheet roof the decision is rarely between good and bad; it is between two kinds of disruption, and the condition of the sheets decides which is proportionate. Strip-and-re-sheet opens the building up, closes the business below, needs a scaffold or crane position and sends a whole roof to disposal over a programme of weeks. A fluid-applied silicone overcoat leaves the sheets in place, keeps the business trading, arrives on one pallet and takes days. It suits exactly this case: sheets that are sound, with a surface that is not.
The system
Gaco S42 and SF42 are 100% silicone liquid-applied roof coatings — not spray foam, and not acrylic. Silicone does not re-emulsify in standing water, which is what makes it the right chemistry for a shaded London roof that never quite dries out. The system was built in layers, each doing one job:
- Biocidal wash to the whole roof, to kill and remove moss, lichen and organic matter so the coating bonds to sheet, not to growth.
- Gaco Patch to the rooflight upstands and any gap over 6 mm — a fibre-reinforced silicone for high-movement details.
- Gaco SF42 to every side lap, end lap, junction and fastener line. SF42 is fibre-reinforced, so no separate scrim or mesh is needed.
- Gaco S4200 Series silicone, white, as the full field coat over the detailed work and the bare sheet, to the film build the 20-year warranty requires.
The white finish was specified deliberately. A reflective roof throws solar gain back off the building instead of driving it into the space below — worth having over a gym full of people generating their own heat.
The installation
The works were carried out by Mass Construction Project Solutions Ltd, a Duratite Approved Contractor for coatings, between 7 and 17 August 2026, using the Gaco silicone system supplied by Duratite Building Products. Hemmed in by neighbouring buildings, the roof had no crane position and no laydown area: everything arrived on one pallet and went up by hand. Brush and roller application meant no spray drift onto adjoining property.
The order of work matters more than anything else on a roof like this. Coat the field first and the joints stay the weak point; detail the joints first and the field coat lands on a roof that is already continuous. So the sequence was survey and measure, biocidal clean, patch and reinforce, then the field coats bay by bay. Wet film comb gauge readings were taken through both coats to confirm the build the warranty is issued against. What went to site: 10 pails of S4200 white, 2 pails of SF42 seam seal and 3 pails of Gaco Patch, on one pallet.
The Outcome
Roughly 200 m² of tired profiled sheeting is now a single continuous, solar-reflective silicone membrane. The rooflight upstands, the laps and the felt junction — every place water was getting in — sit under reinforced detail work rather than under another patch.
Nothing was stripped, nothing went to landfill, and the gym below did not lose a single trading day. Duratite supplied the system, the specification and the coverage guidance; the approved contractor delivered it. A 20-year manufacturer-backed Gaco material warranty was issued by Duratite Building Products to the building’s owner on completion.
On the roof — the full picture


More Duratite case studies
Norton St Philip, Bath Retail — Asbestos Roof EncapsulationAsbestos Roof Encapsulation — Flourish Farm Shop, Norton St Philip, Bath
Read the case study
Harlow, Essex Commercial warehouse — Internal Asbestos EncapsulationInternal Asbestos Roof Encapsulation — IT Luggage, Harlow
Read the case study
Stockport, Greater Manchester Commercial warehouse — Asbestos Roof EncapsulationAsbestos Roof Encapsulation — Stockport, Greater Manchester
Read the case studyHave a similar metal roof waterproofing project?